|
1 | | The second step in the project control process for measuring and evaluating project performance is to |
| | A) | Review the baseline plan with top management |
| | B) | Analyze inputs to control system |
| | C) | Compare plan against actual |
| | D) | Measure progress and performance |
| | E) | Review spending with team members |
|
|
|
2 | | A ___________ Gantt chart is a simple and effective way to depict progress on a project. |
| | A) | Baseline |
| | B) | Control |
| | C) | Variance |
| | D) | Tracking |
| | E) | Simple |
|
|
|
3 | | A tool used to monitor past project schedule performance, current performance, and to estimate future schedule trends is a simple line chart known as a |
| | A) | Project control chart |
| | B) | Gantt chart |
| | C) | PERT chart |
| | D) | Network diagram |
| | E) | Milestone chart |
|
|
|
4 | | The earned value system starts with the time-phased costs that provide the project baseline, which is called the |
| | A) | Planned budgeted value of work scheduled |
| | B) | Planned budgeted value of work completed |
| | C) | Earned value of work scheduled |
| | D) | Scheduled value of work scheduled |
| | E) | Scheduled value of work completed |
|
|
|
5 | | The cost variance for a project is calculated by |
| | A) | EV-AC |
| | B) | AC-SV |
| | C) | PV-EV |
| | D) | CV-EV |
| | E) | EV-PV |
|
|
|
6 | | Baseline project budgets are derived from |
| | A) | The organization's overall budget |
| | B) | Time-phasing the work packages |
| | C) | Top management directions |
| | D) | The total direct, direct project overhead and G&A overhead costs |
| | E) | The earned value system |
|
|
|
7 | | Of the following costs, which are NOT included in baseline? |
| | A) | Suppliers |
| | B) | Equipment |
| | C) | Labor |
| | D) | Budget reserves |
| | E) | Contractors |
|
|
|
8 | | Which of the following methods will measure the cost efficiency of the work accomplished to date? |
| | A) | SV/CV |
| | B) | EV/PV |
| | C) | EV/AC |
| | D) | AC/SV |
| | E) | AC/CV |
|
|
|
9 | | A CPI or SPI value less than one indicates that the project is |
| | A) | Under cost or behind schedule |
| | B) | Over cost or ahead of schedule |
| | C) | Under cost or ahead of schedule |
| | D) | Over cost or behind schedule |
| | E) | On cost or on schedule |
|
|
|
10 | | The value that tells you the planned value of work that has actually been completed is the |
| | A) | SV |
| | B) | PV |
| | C) | EV |
| | D) | AC |
| | E) | CV |
|
|
|
11 | | The indicator that tells you the amount each remaining dollar must earn in order for the project to stay within budget is the |
| | A) | PCIC |
| | B) | VAC |
| | C) | CPI |
| | D) | SPI |
| | E) | TCPI |
|
|
|
12 | | Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the |
| | A) | SV |
| | B) | TCPI |
| | C) | CPI |
| | D) | SPI |
| | E) | PCIB |
|
|
|
13 | | Sally receives the following information on her project: PV=100, AC=75, EV=100. How well is the project doing in terms of budget? |
| | A) | Right on budget |
| | B) | 25 under budget |
| | C) | 25 over budget |
| | D) | 50 under budget |
| | E) | 50 over budget |
|
|
|
14 | | Jessica just received the following information on her project: PV =200, EV=300, AC=250, BAC=1500, EAC=1208. In terms of cost at completion |
| | A) | The project will currently finish under budget |
| | B) | The project will currently finish over budget |
| | C) | The project will currently finish on budget |
| | D) | The project will currently finish behind schedule |
| | E) | There is insufficient information to draw conclusions |
|
|
|
15 | | Which of the following is NOT true regarding scope creep? |
| | A) | It commonly occurs late in projects |
| | B) | It is frequently unnoticed until time delays or cost overruns are observed |
| | C) | It wears down team motivation and cohesiveness |
| | D) | Project suppliers resent frequent changes |
| | E) | Scope changes can represent significant opportunity |
|
|