|
1 | | Which of the following represents an activity on an AON project network? |
| | A) | An arrow |
| | B) | A line |
| | C) | A node |
| | D) | Both an arrow and a line |
| | E) | An arrow, a line and a node all represent activities |
|
|
|
2 | | When translated into a project network, a work package will become |
| | A) | A single activity |
| | B) | One or more activities |
| | C) | A milestone |
| | D) | A critical path |
| | E) | An arrow |
|
|
|
3 | | Which of the following is provided by both the project network and the work breakdown structure? |
| | A) | Dependencies |
| | B) | Sequencing |
| | C) | Interrelationships |
| | D) | Activity duration |
| | E) | Timing |
|
|
|
4 | | On a project network, the activity times are derived from the |
| | A) | Organization breakdown structure |
| | B) | Work packages |
| | C) | Budget |
| | D) | Project proposal |
| | E) | Responsibility matrix |
|
|
|
5 | | An activity that has more than one dependency arrow flowing into it is termed a(n) |
| | A) | Parallel activity |
| | B) | Critical path |
| | C) | Burst activity |
| | D) | Merge activity |
| | E) | Independent activity |
|
|
|
6 | | Which of the following can be used without coordinating with managers of succeeding activities? |
| | A) | Total slack |
| | B) | Free slack |
| | C) | Critical float |
| | D) | Float pad |
| | E) | Slip pad |
|
|
|
7 | | Activities which can take place at the same time are termed |
| | A) | Parallel activity |
| | B) | Critical path |
| | C) | Burst activity |
| | D) | Merge activity |
| | E) | Independent activity |
|
|
|
8 | | Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity one is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of |
| | A) | Conditional statements |
| | B) | Looping |
| | C) | Having more than one start node |
| | D) | Good network development |
| | E) | Natural network flow |
|
|
|
9 | | ________ activities must be completed immediately before a particular activity. |
| | A) | Merge |
| | B) | Burst |
| | C) | Predecessor |
| | D) | Successor |
| | E) | Parallel |
|
|
|
10 | | The forward pass in project network calculations determines all of the following EXCEPT |
| | A) | Earliest time an activity can begin |
| | B) | Earliest time an activity can be finished |
| | C) | Duration of the project |
| | D) | The critical path |
| | E) | How soon the project can be finished |
|
|
|
11 | | Which of the following correctly calculates the late start for an activity? |
| | A) | EF - DUR |
| | B) | ES - DUR |
| | C) | LF - DUR |
| | D) | ES - SL |
| | E) | LF - SL |
|
|
|
12 | | Which of the following will correctly calculate the total slack in an activity? |
| | A) | LS - ES |
| | B) | LF - EF |
| | C) | LS - LF |
| | D) | LF - ES |
| | E) | Either LS – ES or LF – EF |
|
|
|
13 | | If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first? |
| | A) | Check to see which activities cost the least |
| | B) | Check to see which activities have the longest duration |
| | C) | Check to see which activities are on the critical path |
| | D) | Check to see which activities have the most slack |
| | E) | Check to see which activities have the highest risk |
|
|
|
14 | | If a project has more than one activity that can begin when the project is to start a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a |
| | A) | Critical path |
| | B) | Parallel path |
| | C) | Dangler path |
| | D) | Multiple start path |
| | E) | Confused path |
|
|
|
15 | | Concurrent engineering, which has dramatically reduced the development time for new products, relies of what kind of lag? |
| | A) | Start to Start lags |
| | B) | Start to Finish lags |
| | C) | Finish to Finish lags |
| | D) | Finish to Start lags |
| | E) | Any of these could be correct |
|
|