1 | | A _________ approach actually schedules in detail each resource using the setup and runtime required for each order. |
| | A) | Infinite loading |
| | B) | Finite loading |
| | C) | Forward scheduling |
| | D) | Backward scheduling |
| | E) | None of the above |
|
|
|
2 | | The objectives of work-center scheduling include(s): |
| | A) | To meet due dates |
| | B) | To minimize lead times |
| | C) | To minimize finish goods inventory |
| | D) | A and B |
| | E) | B and C |
| | F) | A, B, and C |
|
|
|
3 | | Which of the following is not a priority rule for job sequencing? |
| | A) | shortest processing time |
| | B) | minimum slack time remaining |
| | C) | last come, first served |
| | D) | critical ratio |
| | E) | all the above are priority rules |
|
|
|
4 | | The first hour principle is best used when |
| | A) | Scheduling two jobs on one machine |
| | B) | Scheduling n jobs on two machines |
| | C) | Applying input output control |
| | D) | Scheduling hourly work times |
| | E) | None of the above |
|
|
|
5 | | The assignment method is appropriate in solving problems that have the following characteristics: |
| | A) | There are 'n' things to be distributed to 'n' destinations |
| | B) | Though each destination may handle all the things, the final assignment has each thing assigned to one and only one destination |
| | C) | Only one criterion should be used (minimum cost, maximum profit, for example) |
| | D) | A and C |
| | E) | A, B, and C |
|
|
|
6 | | The major functions of shop-floor control are: |
| | A) | Assign priority of each shop order |
| | B) | Provide actual output data for capacity control purposes |
| | C) | Maintain work-in-process quantity information |
| | D) | A and B |
| | E) | A, B, and C |
|
|
|
7 | | The basic tools for shop-floor control include: |
| | A) | Dispatch list |
| | B) | Various status and exception reports |
| | C) | An input/output control report |
| | D) | B and C |
| | E) | A, B, and C |
|
|
|
8 | | Which of the following is not a principle of work-center scheduling? |
| | A) | Once started, a job should not be interrupted |
| | B) | Reschedule every day |
| | C) | Schedule jobs as strings, with process steps back to back |
| | D) | There is direct equivalence between work flow and cash flow |
| | E) | Obtain feedback each day on jobs that are completed at each work center |
|
|
|
9 | | In scheduling personnel for services, which of following is not an issue? |
| | A) | Consecutive days off |
| | B) | Johnson's rule |
| | C) | Continuous shifts |
| | D) | Expected customer demand |
| | E) | None of the above |
|
|