1 | ![](/olcweb/styles/shared/spacer.gif) | ![](/olcweb/styles/shared/spacer.gif) The term project is defined as a sequence of activities that must be completed on time, within budget, and at a minimal cost. |
| ![](/olcweb/styles/shared/spacer.gif) | A)![](/olcweb/styles/shared/spacer.gif) | True |
| ![](/olcweb/styles/shared/spacer.gif) | B)![](/olcweb/styles/shared/spacer.gif) | False |
|
|
![](/olcweb/styles/shared/spacer.gif) |
2 | ![](/olcweb/styles/shared/spacer.gif) | ![](/olcweb/styles/shared/spacer.gif) The scope of process management is all projects, whereas the scope of project management is a single project. |
| ![](/olcweb/styles/shared/spacer.gif) | A)![](/olcweb/styles/shared/spacer.gif) | True |
| ![](/olcweb/styles/shared/spacer.gif) | B)![](/olcweb/styles/shared/spacer.gif) | False |
|
|
![](/olcweb/styles/shared/spacer.gif) |
3 | ![](/olcweb/styles/shared/spacer.gif) | ![](/olcweb/styles/shared/spacer.gif) A project is considered successful if the resulting information system is developed at the lowest possible cost. |
| ![](/olcweb/styles/shared/spacer.gif) | A)![](/olcweb/styles/shared/spacer.gif) | True |
| ![](/olcweb/styles/shared/spacer.gif) | B)![](/olcweb/styles/shared/spacer.gif) | False |
|
|
![](/olcweb/styles/shared/spacer.gif) |
4 | ![](/olcweb/styles/shared/spacer.gif) | ![](/olcweb/styles/shared/spacer.gif) Feature creep is the unexpected and gradual growth of requirements during an information systems project, while scope creep is the uncontrolled addition of technical features to a system. |
| ![](/olcweb/styles/shared/spacer.gif) | A)![](/olcweb/styles/shared/spacer.gif) | True |
| ![](/olcweb/styles/shared/spacer.gif) | B)![](/olcweb/styles/shared/spacer.gif) | False |
|
|
![](/olcweb/styles/shared/spacer.gif) |
5 | ![](/olcweb/styles/shared/spacer.gif) | ![](/olcweb/styles/shared/spacer.gif) Among the basic functions of a project manager are scoping, planning, directing, estimating, scheduling, programming, and closing. |
| ![](/olcweb/styles/shared/spacer.gif) | A)![](/olcweb/styles/shared/spacer.gif) | True |
| ![](/olcweb/styles/shared/spacer.gif) | B)![](/olcweb/styles/shared/spacer.gif) | False |
|
|
![](/olcweb/styles/shared/spacer.gif) |
6 | ![](/olcweb/styles/shared/spacer.gif) | ![](/olcweb/styles/shared/spacer.gif) A PERT chart is a graphical network model that depicts a project’s tasks and the relationships between those tasks. |
| ![](/olcweb/styles/shared/spacer.gif) | A)![](/olcweb/styles/shared/spacer.gif) | True |
| ![](/olcweb/styles/shared/spacer.gif) | B)![](/olcweb/styles/shared/spacer.gif) | False |
|
|
![](/olcweb/styles/shared/spacer.gif) |
7 | ![](/olcweb/styles/shared/spacer.gif) | ![](/olcweb/styles/shared/spacer.gif) One of the key objectives of Joint Project Planning (JRP) is to have all stakeholders reach consensus on the business requirement statement for the project. |
| ![](/olcweb/styles/shared/spacer.gif) | A)![](/olcweb/styles/shared/spacer.gif) | True |
| ![](/olcweb/styles/shared/spacer.gif) | B)![](/olcweb/styles/shared/spacer.gif) | False |
|
|
![](/olcweb/styles/shared/spacer.gif) |
8 | ![](/olcweb/styles/shared/spacer.gif) | ![](/olcweb/styles/shared/spacer.gif) Statement of work depicts the hierarchical decomposition of a project into phases, activities, and tasks. |
| ![](/olcweb/styles/shared/spacer.gif) | A)![](/olcweb/styles/shared/spacer.gif) | True |
| ![](/olcweb/styles/shared/spacer.gif) | B)![](/olcweb/styles/shared/spacer.gif) | False |
|
|
![](/olcweb/styles/shared/spacer.gif) |
9 | ![](/olcweb/styles/shared/spacer.gif) | ![](/olcweb/styles/shared/spacer.gif) Pessimistic duration is the estimation of the maximum amount of time that it would take to perform a task. |
| ![](/olcweb/styles/shared/spacer.gif) | A)![](/olcweb/styles/shared/spacer.gif) | True |
| ![](/olcweb/styles/shared/spacer.gif) | B)![](/olcweb/styles/shared/spacer.gif) | False |
|
|
![](/olcweb/styles/shared/spacer.gif) |
10 | ![](/olcweb/styles/shared/spacer.gif) | ![](/olcweb/styles/shared/spacer.gif) A Gantt chart is the most commonly used project scheduling and progress evaluation tool. |
| ![](/olcweb/styles/shared/spacer.gif) | A)![](/olcweb/styles/shared/spacer.gif) | True |
| ![](/olcweb/styles/shared/spacer.gif) | B)![](/olcweb/styles/shared/spacer.gif) | False |
|
|