|
1 | | Proactive risk management is sometimes described as fire fighting. |
| | A) | True |
| | B) | False |
|
|
|
2 | | Software risk always involves two characteristics |
| | A) | fire fighting and crisis management |
| | B) | known and unknown risks |
| | C) | uncertainty and loss |
| | D) | staffing and budget |
|
|
|
3 | | Three categories of risks are |
| | A) | business risks, personnel risks, budget risks |
| | B) | project risks, technical risks, business risks |
| | C) | planning risks, technical risks, personnel risks |
| | D) | management risks, technical risks, design risks |
|
|
|
4 | | Generic risks require far more attention than product-specific risks. |
| | A) | True |
| | B) | False |
|
|
|
5 | | A risk item checklist would contain known and predictable risks from which of these categories? |
| | A) | product size |
| | B) | development environment |
| | C) | staff size |
| | D) | process definition |
| | E) | all of the above |
|
|
|
6 | | Questions that should be asked to assess the overall project risk include: |
| | A) | Have top managers formally committed to support the project? |
| | B) | Are end-users committed to the project and proposed system being built? |
| | C) | Are requirement fully understood by development team and customers? |
| | D) | Does the proposed budget have time allocated for marketing? |
| | E) | a, b, c |
|
|
|
7 | | Software risk impact assessment should focus on consequences affecting |
| | A) | planning, resources, cost, schedule |
| | B) | marketability, cost, personnel |
| | C) | business, technology, process |
| | D) | performance, support, cost, schedule |
|
|
|
8 | | Risk projection attempts to rate each risk in two ways |
| | A) | likelihood and cost |
| | B) | likelihood and impact |
| | C) | likelihood and consequences |
| | D) | likelihood and exposure |
|
|
|
9 | | Risk tables are sorted by |
| | A) | probability and cost |
| | B) | probability and impact |
| | C) | probability and consequences |
| | D) | probability and exposure |
|
|
|
10 | | Individual team members can make their own estimate for a risk probability and then develop a consensus value. |
| | A) | True |
| | B) | False |
|
|
|
11 | | Which factors affect the probable consequences likely if a risk does occur? |
| | A) | risk cost |
| | B) | risk timing |
| | C) | risk scope |
| | D) | risk resources |
| | E) | b and c |
|
|
|
12 | | The reason for refining risks is to break them into smaller units having different consequences. |
| | A) | True |
| | B) | False |
|
|
|
13 | | Effective risk management plan needs to address which of these issues? |
| | A) | risk avoidance |
| | B) | risk monitoring |
| | C) | contingency planning |
| | D) | all of the above |
|
|
|
14 | | Risk monitoring involves watching the risk indicators defined for the project and not determining the effectiveness of the risk mitigation steps themselves. |
| | A) | True |
| | B) | False |
|
|
|
15 | | Hazard analysis focuses on the identification and assessment of potential hazards that can cause |
| | A) | project termination |
| | B) | schedule slippage |
| | C) | cost overruns |
| | D) | an entire system to fail |
|
|
|
16 | | Risk information sheets (RIS) are never an acceptable substitute for a full risk mitigation, monitoring, and management (RMMM) plan. |
| | A) | True |
| | B) | False |
|
|