Site MapHelpFeedbackKey Terms
Key Terms
(See related pages)


Cost performance index (CPI)  The ratio of budgeted costs to actual costs (BCWP/ACWP).
Cost variance (CV)  The difference between BCWP and ACWP (CV _ BCWP _ACWP). Tells if the work accomplished cost more or less than was planned at any point over the life of the project.
Earned value (EV)  The physical work accomplished plus the authorized budget for this work. Previously this was called the budgeted cost of work performed (BCWP).
Schedule variance (SV)  The difference between the planned dollar value of the work actually completed and the value of the work scheduled to be completed at a given point in time (SV _ BCWP _ BCWS). Schedule variance contains no critical path information.
Time-phased budgets  Planned costs that are broken down by distinct time periods (e.g., $5,000 per week) for a work package, as opposed to a budget for a whole job/project (6 months for a total of $130,000). Time phasing allows better cost control by measuring the actual rate of expenditure versus the planned expenditure rate over small pieces of the project.
Variance at completion (VAC)  Indicates expected actual cost over- or underrun at completion (VAC _ BAC _ EAC).
Estimated cost at completion (EAC)  The sum of actual costs to date plus revised estimated costs for the work remaining in the WBS.







Project Management, 3/eOnline Learning Center

Home > Chapter 13 > Key Terms