Site MapHelpFeedbackSelf Quiz
Self Quiz
(See related pages)



1

A project monitoring system involves all of the following except
A)determining what data to collect
B)determining how, when, and who will collect the data
C)adjusting the data
D)analyzing of the data
E)reporting current progress
2

A typical project progress report would contain all of the following sections except
A)progress since the last report
B)problems and issues since the last report
C)current status of the project
D)corrective action planned
E)all of these are typical sections
3

The third step in the project control process of measuring and evaluating of project performance is to
A)review the baseline plan with top management
B)analyze inputs to the control system
C)compare the plan against actual performance
D)measure both progress and performance
E)review spending with team members
4

A tool used to monitor past project schedule performance, current performance, and to estimate future schedule trends is a simple line chart known as a
A)project schedule control chart
B)Gantt chart
C)PERT chart
D)network diagram
E)milestone chart
5

The earned value of a project is the
A)project cost to date adjusted for project scope changes
B)total project cost to date
C)cost incurred minus the planned cost
D)percent of the original budget that has been earned by actual work
E)none of these are correct
6

The cost variance for a project is calculated by
A)EV-AC
B)AC-SV
C)PV-EV
D)CU-EV
E)EU-PV
7

Baseline project budgets are derived from
A)the organization's overall budget
B)time-phasing the work packages
C)top management directions
D)both A and C are correct
E)A, B, and C are all correct
8

Of the following costs, which may not be included in baseline?
A)materials
B)equipment
C)DOC
D)labor
E)all of these are usually included
9

Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?
A)BAC
B)EAC
C)ETC
D)VAC
E)TCPI
10

Which of the following methods will measure the scheduling efficiency of the work accomplished to date?
A)SV/CV
B)EV/PV
C)EV/AC
D)AC/SV
E)AC/CV
11

The percent complete index that looks at percent complete in terms of budgeted amounts is calculated by which of the following?
A)EV/BAC
B)(EV-PV)/BAC
C)AC/EAC
D)(EV-AC)/BAC
E)(EV-PV)/EAC
12

Which of the following will calculate the estimated cost to complete the project?
A)(VAC-EV)/(PV/AC)
B)(BAC-EV)/(EV/AC)
C)(PV/AC)/(VAC-EV)
D)(EV/AC)/(BAC-EV)
E)(BAC-EV)/(BAC-AC)







Project Management, 3/eOnline Learning Center

Home > Chapter 13 > Self Quiz