A critical factor to ensure the success of integrating the strategic plan with projects lies in a process that
A)is open and published for all participants to review
B)starts with top management's directives
C)with projects first and integrates them with the strategic plan
D)both b and c are correct
E)a, b, and c are all correct
2

Which of the following is a main reason why project managers need to understand their organization's mission and strategy?
A)They can better focus on the immediate customer.
B)They can make appropriate decisions and adjustments.
C)So they can be effective project advocates.
D)both B and C are correct
E)A, B, and C are all correct
3

The textbook indicated that ________is the major dimension of strategic management.
A)responding to changes in the external market
B)allocating scarce resources of the organization
C)beating competition to the market
D)both a and b are correct
E)both a and c are correct
4

Which of the following is the correct order for the strategic management process?
A)strategies, mission, goals, projects
B)goals, projects, mission, strategies
C)mission, goals, strategies, projects
D)goals, mission, strategies, projects
E)projects, mission, strategies, goals
5

Which of the following is not one of the traditional components found in mission statements?
A)major products and services
B)profitability
C)target customers and markets
D)geographic domain
E)contribution to society
6

Which of the following is not one of the characteristics of effective objectives?
A)Realistic
B)Assignable
C)Flexible
D)Specific
E)Measurable
7

The assessment of the external and internal environments is called _______ analysis.
A)SWOT analysis
B)competitive
C)industry
D)market
E)strategic
8

Which of the following is not one of the requirements for successful implementation of strategies through projects?
A)allocation of resources
B)prioritizing of projects
C)motivation of project contributors
D)adequate planning and control systems
E)all of these are requirements
9

Which of the following terms is often used to denote a project that a powerful, high-ranking official is advocating?
A)sacred cow
B)pet project
C)political necessity
D)special undertaking
E)strategic ploy
10

Which of the following financial models are typically included in project selection?
A)payback
B)net present value
C)Internal rate of return
D)both a and b are correct
E)a, b, and c are all correct
11

Projects are usually classified into all but one of the following categories. Which one is not one of the typical classifications?
A)compliance and emergency
B)operational
C)strategic
D)political necessity
E)all of these are typical classifications
12

Which of the following is not true of multi-weighted scoring models?
A)will include quantitative criteria
B)will include qualitative criteria
C)each criterion is assigned a weight
D)projects with higher scores are considered more desirable
E)All of the above are true