1
Which of the following is not a basic process flow structure?
A)Work Center
B)Mass Attack
C)Assembly Line
D)Project Layout
E)Continuous Process
2
The type of processing structure that is used to produce gasoline, chemicals, and drugs is:
A)Work Center
B)Batch
C)Assembly Line
D)Project Layout
E)Continuous Process
3
The type of processing structure that is used for producing discrete products at higher volume is:
A)Work Center
B)Batch
C)Assembly Line
D)Project Layout
E)Continuous Process
4
The best description of the process structure used for assembling the Space Shuttle is:
A)Work Center
B)Manufacturing Cell
C)Assembly Line
D)Project Layout
E)Continuous Process
5
The major decision variables in equipment selection are:
A)Flexibility
B)Labor requirements
C)Manufacturer
D)Both A and B
E)Both B and C
6
When comparing multiple processes to manufacture a product, the path of lowest total cost is always a straight line.
A)True
B)False
7
The product-process matrix:
A)shows as volume decreases an assembly line is the solution
B)shows as volume increase specialized equipment becomes cost effective
C)shows all process structures except work centers are inefficient
D)guides companies on what products to produce
E)allows a manager to justify buying new equipment
8
A process flow diagram shows how parts are put together to make a product.
A)True
B)False
9
A breakeven point indicates which of the following:
A)The point where profit is maximized
B)The point where cost is minimized
C)The point where we are indifferent between two options
D)The point where we are most efficient
E)All of the above