Problems 1. A project consists of 10 activities, lettered A through J, as shown in the accompanying precedence diagram, with the activities on the arrows. For each activity, the deterministic time estimate in weeks is shown in the following table. | Activity | | Time | | Activity | | Time | | A B C D E | | 2 4 3 5 6 | | F G H I J | | 3 4 4 3 1 |
- List all of the paths through the network.
- What is the duration of each of the paths?
- What is the critical path?
- What is the second-most critical path?
- What is the slack time for each activity?
- Calculate the ES, Ef, LS and LF times for each activity.
2. A project consists of 11 activities, lettered A through K, below. For each activity, the preceding activity is given, and a deterministic estimate of the length of time required to complete it in weeks. | Activity | Time | Preceding Activity | Activity | Time | Preceding Activity | | A | 1 week | - | G | 4 weeks | E | | B | 3 | A | H | 6 | F | | C | 2 | A | I | 2 | G | | D | 4 | C | J | 1 | H,I | | E | 2 | - | K | 1 | B,D,J | | F | 3 | E | | | |
- Draw the precedence network for this project, with the activities on the
arrows.
- List all of the paths through the network.
- What is the duration of each of the paths?
- What is the critical path?
- What is the slack time for each activity?
- The materials required to accomplish activity F have been delayed for two
weeks by a strike at the supplier's plant. What effect will this have on the
length of time required to complete the project?
- An equipment breakdown has delayed activity B for one week. What effect will
this have on the length of time required to complete the project?
3. A project consists of 8 activities, lettered A through H. below. For each activity, the preceding activity is given, and a probabilistic estimate of the time required to complete it. Times are in days. | | Preceding | Optimistic | Most Likely | Pessimistic | | Activity | Activity | Time | Time | Time | | A | -- | 2 days | 4 days | 6 days | | B | A | 3 | 6 | 9 | | C | A | 2 | 5 | 11 | | D | -- | 2 | 10 | 12 | | E | C, | 4 | 8 | 15 | | F | B,E | 2 | 4 | 12 | | G | D | 3 | 4 | 11 | | H | F,G | 1 | 1 | 1 |
- Determine the expected time for each activity.
- Determine the variance for each activity
- Draw the PERT network for this project, with the activities on the arrows.
- List all of the paths through the network.
- What is the duration of each path?
- What is the variance of each path?
- What is the critical path?
- What is the second-most critical path?
- Activity D was delayed three days by an earthquake in the area. What effect
does this have on the length of time required to complete the project?
4. Refer to Problem 3 and the original critical path before the earthquake. - What is the mean of the probability distribution for the completion time?
- What is the standard deviation of the probability distribution for the completion
time?
- What is the probability of finishing the project within 24 days?
- What is the probability of finishing the project within 22 days?
- What is the probability that the project will take longer than 28 days?
5. After the earthquake, in Problem 3-i., management faced the problem of how to make up the lost time, and how much it would cost. Estimates of crash times and costs for each activity are given below. | Activity | Crash Time | Cost per Day | | A | Not possible | - | | B | 3 days | $200 per day | | C | not possible | - | | D | not possible* | - | | E | 5 days | $300 per day | | F | 2 days | $500 per day | | G | not possible | - | | H | not possible | - |
*(because of the earthquake) - Which activity should be crashed?
- How many days should it be crashed?
- How much will it cost?
6. Construct the PERT network for Problem 3 with the activities on the nodes. Solutions 1. a, b. | Path | Duration (weeks) | | A-B-C-I-J A-D-F-I-J A-D-G-H-J E-F-I-J E-G-H-J | 2 + 4 + 3 + 3 + 1 = 13 2 + 5 + 3 + 3 + 1 = 14 2 + 5 + 4 + 4 + 1 = 16 6 + 3 + 3 + 1 = 13 6 + 4 + 4 + 1 = 15 |
c. The critical path is #3.
d. The second-most critical path is #5.
e. The slack is the difference between the duration of the critical path and
the duration of each alternative path. When an activity appears on more than
one path, the slack is the smallest difference. | Activity | Path | Slack (wk.) | Activity | Path | Slack (Wk.) | | A B C D E | 3 1 1 3 5 | 0 3 3 0 1 | F G H I J | 2 3 3 2 3 | 2 0 0 2 0 |
f. | Activity | ES | EF | LS | LF | Slack (wk.) | | A B C D E F G H I J | 0 2 6 2 0 7 7 11 10 15 | 2 6 9 7 6 10 11 15 13 16 | 0 5 9 2 1 9 7 1 2 5 | 2 9 12 7 7 12 11 15 15 16 | 0 3 3 0 1 2 0 0 2 0 |
2. a. b, c. | Path | Duration (weeks) | | A-B-DI-DII-K A-C-D-DII-K E-F-H-J-K E-G-I-J-K | 1 + 3 + 0 + 0 + 1 = 5 1 + 2 + 4 + 0 + 1 = 8 2 + 3 + 6 + 1 + 1 = 13 2 + 4 + 2 + 1 + 1 = 10 |
d. The critical path is #3, with a duration of 13 weeks. e. | Activity | Path | Slack (wk.) | Activity | Path | Slack (wk.) | | A B C D DI DII E | 2 1 2 2 1 2 3 | 5 8 5 5 8 5 0 | F G G I J K | 3 4 3 4 3 3 | 0 3 0 3 0 0 |
f. It will delay the completion of the project by 2 weeks.
g. It will have no effect on the completion of the project. - a, b. For activity A: Image141 (1.0K)Image141 days.
Repeat for each activity. For activity A: Image142 (1.0K)Image142 . Repeat for each activity. | Activity | Expected time (days) | Variance | Activity | Expected Time (days) | Variance | | A B C D | 4 6 5.5 9 | 0.4444 1.0000 2.2500 2.7778 | E F G H | 8.5 5 5 1 | 3.3611 2.7778 1.7778 0 |
c. d, e. There are four paths through the network. | Path | Duration (days) | | A-B-DI-F-H A-C-E-F-H D-DII-E-F-H D-G-DIII-H | 4 + 6 + 0 + 5 + 1 = 16 4 + 5.5 + 8.5 + 5 + 1 = 24 9 + 0 + 8.5 + 5 + 1 = 23.5 9 + 5 + 0 + 1 = 15 |
f. The variance for each path is obtained by adding the variances of the activities
on the path. For Path #1) Variance = .4444 + 1.0000 + 0 + 2.7778 + 0 = 4.2222.
Repeat for each path.
| Path | Variance | | 1) 2) 3) 4) | 4.2222 8.8333 8.9167 4.5556 |
g. The critical path is #2, with a duration , Image143 (0.0K)Image143
days.
h. The second-most critical path is #3, with a duration of 23.5 days.
i. The duration along the path, D - DII - E - F - H, is increased to 26.5 days.
Because this total is larger than 24 days, this constitutes a new critical path. 4. a. The mean is the longest duration, or 24 days.
b. Image144 (1.0K)Image144 .
c. Find the value of z in order to read the table of the areas of the standardized
normal curve: Image145 (1.0K)Image145 Image146 (1.0K)Image146 .
d. Image147 (1.0K)Image147 Image148 (1.0K)Image148 . e.Image149 (1.0K)Image149 Image150 (1.0K)Image150 . 5. a. Activity E should be crashed because it is on the critical path and crashing
it would be less expensive than crashing activity F.
b. Activity E should be crashed for 3 days to make up for the earthquake.
c. The expense will be: 3 days x $200 = $600. 6. 7. From Monday, May 1 to Friday, August 11 is 15 work weeks; set the last LS equal to 15. | Activity | ES | EF | LS | LF | Slack (wk.) | | A B C D DI DII E F G H I J K | 0 1 1 3 4 7 0 2 2 5 6 11 12 | 1 4 3 7 4 7 2 5 6 11 18 12 13 | 7 1 8 0 4 4 2 4 7 7 11 13 14 | 8 14 10 14 14 14 4 7 11 13 13 14 15 | 7 10 7 7 10 7 2 2 5 2 5 2 2 |
|